{"audience":"Maintenance planners, maintenance managers, work center leads and reliability engineers who update task list durations.","authorization_objects":[{"note":"Display maintenance orders by planning plant","object":"I_IWERK"},{"note":"Maintenance order authorization by order type","object":"I_AUART"}],"components":[],"countries":[],"effort_days_max":4,"effort_days_min":3,"effort_size":"S","faq":[{"a":"By default only internal labor operations (control key for internal processing) are evaluated. External service operations are excluded because they are tracked through service entry sheets; they can be listed with a separate option if needed.","q":"Are external service operations included?"},{"a":"Yes. The average actual work of operations from the same task list can be shown in a separate summary view; operations that deviate consistently are flagged as candidates for updating the planned work in the task list.","q":"Can the result be used to update task list durations?"},{"a":"Yes. AFIH, AFVC, AFVV and AFRU keep the same structure in S/4HANA. For a clean core approach, released CDS views such as I_MaintOrderOperationData and I_MaintOrdConfirmationCube can be used.","q":"Does the report work on S/4HANA?"}],"features":[{"code":"alv","label":"ALV list (sort, filter, subtotals)","note":""},{"code":"layout","label":"User-specific layout variants","note":""},{"code":"drilldown","label":"Double-click drill-down to the document","note":"The order opens IW33; the confirmation count opens the operation's confirmations in the IW47 list."},{"code":"excel","label":"Export to Excel","note":""},{"code":"background","label":"Runs as a background job","note":""}],"functions":[],"gap":"IW37N lists operations with planned and actual work and IW47 shows confirmations; but there is no variance percentage, no tolerance filter, no conversion of different work units to hours and no summary by work center or activity type. The number of technicians who confirmed is not visible on the operation line either. For a planning accuracy KPI, users combine the two lists in Excel. The custom report does this calculation.","id":"pm-planned-vs-actual-work-hours","industries":[],"input_columns":[],"kind":"report","language":"en","lastmod":"2026-11-17","logic":"1. Maintenance orders of the selected planning plant, planner group and activity type are read from AFIH, with order type, short text and object number from AUFK; with 'only completed' selected, orders with TECO (I0045) active in JEST are kept.\n2. Through AFKO-AUFPL the AFVC operations (work center, control key, text) are read, and AFVV gives planned work (ARBEI), actual work (ISMNW), remaining work (OFMNW) and the work unit (ARBEH).\n3. Non-reversed confirmations (STOKZ blank, STZHL = 0) within the confirmation date range are read from AFRU by the operation's confirmation number; the number of confirmations and of distinct personnel numbers (PERNR) is counted.\n4. Different work units (minutes, days) are converted to hours; variance = actual − planned, variance percentage = variance ÷ planned × 100.\n5. The work center is read from CRHD-ARBPL; lines with an absolute variance percentage below the tolerance can be hidden.\n6. The list is per operation; ALV subtotals give the planning accuracy per work center, activity type and order type.","module":"PM","object_type":"alv_report","output_columns":[{"calculated":false,"formula":"","label":"Order","source_field":"AUFNR","source_table":"AUFK"},{"calculated":false,"formula":"","label":"Short text","source_field":"KTEXT","source_table":"AUFK"},{"calculated":false,"formula":"","label":"Order type","source_field":"AUART","source_table":"AUFK"},{"calculated":false,"formula":"","label":"Activity type","source_field":"ILART","source_table":"AFIH"},{"calculated":false,"formula":"","label":"Equipment","source_field":"EQUNR","source_table":"AFIH"},{"calculated":false,"formula":"","label":"Operation","source_field":"VORNR","source_table":"AFVC"},{"calculated":false,"formula":"","label":"Operation text","source_field":"LTXA1","source_table":"AFVC"},{"calculated":false,"formula":"","label":"Work center","source_field":"ARBPL","source_table":"CRHD"},{"calculated":false,"formula":"","label":"Planned work","source_field":"ARBEI","source_table":"AFVV"},{"calculated":false,"formula":"","label":"Actual work","source_field":"ISMNW","source_table":"AFVV"},{"calculated":false,"formula":"","label":"Unit","source_field":"ARBEH","source_table":"AFVV"},{"calculated":false,"formula":"","label":"Remaining work","source_field":"OFMNW","source_table":"AFVV"},{"calculated":true,"formula":"ISMNW − ARBEI converted to hours","label":"Variance (hours)","source_field":null,"source_table":null},{"calculated":true,"formula":"Variance ÷ planned work × 100","label":"Variance (%)","source_field":null,"source_table":null},{"calculated":true,"formula":"Number of valid AFRU records","label":"Confirmations","source_field":null,"source_table":null},{"calculated":true,"formula":"Number of distinct AFRU-PERNR","label":"Technicians","source_field":null,"source_table":null}],"parameters":[{"example":"1000","kind":"select_option","label":"Planning plant","name":"S_IWERK","ref_field":"AFIH-IWERK","required":true},{"example":"M01","kind":"select_option","label":"Planner group","name":"S_INGPR","ref_field":"AFIH-INGPR","required":false},{"example":"PM01, PM02","kind":"select_option","label":"Order type","name":"S_AUART","ref_field":"AUFK-AUART","required":false},{"example":"002","kind":"select_option","label":"Maintenance activity type","name":"S_ILART","ref_field":"AFIH-ILART","required":false},{"example":"MEKANIK","kind":"select_option","label":"Work center","name":"S_ARBPL","ref_field":"CRHD-ARBPL","required":false},{"example":"01.10.2026 – 31.10.2026","kind":"select_option","label":"Confirmation date","name":"S_BUDAT","ref_field":"AFRU-BUDAT","required":true},{"example":"20","kind":"parameter","label":"Tolerance (%)","name":"P_TOL","ref_field":"","required":false},{"example":"X","kind":"checkbox","label":"Only TECO orders","name":"P_DONE","ref_field":"","required":false}],"part_of":["pm-notification-to-confirmation-pack"],"performance":"Fetch AFIH and AUFK with one joined read, and AFVC/AFVV with FOR ALL ENTRIES on the AUFPL list. Restrict the AFRU read by the confirmation date range. For yearly analyses, run the report in the background.","quote_url":"https://nekuhub.com/en/request-a-quote/?report=pm-planned-vs-actual-work-hours","related":["pm-overdue-maintenance-orders-backlog","pm-time-confirmation-upload"],"releases":[],"source":"custom","standard_alternatives":[{"note":"Lists operations with planned and actual work; there is no variance percentage, unit conversion or tolerance filter.","tcode":"IW37N"},{"note":"Lists confirmations; does not compare with planned work.","tcode":"IW47"}],"summary":"A custom ALV report that compares planned work with confirmed actual work on maintenance order operations and shows the variance in hours and percent by work center, maintenance activity type and equipment. The number of confirmations and technicians is on the same line, so the accuracy of planning estimates and task list durations is measured in one list.","tables":[{"access":"read","join_on":"","role":"Maintenance order header: planning plant, planner group, activity type, equipment (driving table)","table":"AFIH","variant":"both"},{"access":"read","join_on":"AUFK-AUFNR = AFIH-AUFNR","role":"Order type, short text, object number","table":"AUFK","variant":"both"},{"access":"read","join_on":"AFKO-AUFNR = AFIH-AUFNR","role":"Routing number of operations","table":"AFKO","variant":"both"},{"access":"read","join_on":"AFVC-AUFPL = AFKO-AUFPL","role":"Operation: work center, text, confirmation number","table":"AFVC","variant":"both"},{"access":"read","join_on":"AFVV-AUFPL = AFVC-AUFPL AND AFVV-APLZL = AFVC-APLZL","role":"Planned, actual and remaining work","table":"AFVV","variant":"both"},{"access":"read","join_on":"AFRU-RUECK = AFVC-RUECK AND AFRU-STOKZ = ' '","role":"Confirmations: count and technicians","table":"AFRU","variant":"both"},{"access":"read","join_on":"CRHD-OBJTY = 'A' AND CRHD-OBJID = AFVC-ARBID","role":"Work center of the operation","table":"CRHD","variant":"both"},{"access":"read","join_on":"JEST-OBJNR = AUFK-OBJNR AND JEST-INACT = ' '","role":"TECO status","table":"JEST","variant":"both"}],"title":"Maintenance Order Planned vs Actual Work Hours Report","url":"https://nekuhub.com/en/reports/maintenance-order-planned-vs-actual-work-hours-report/","vendor_id":"nekudos"}