# WBS Plan Cost vs Original Budget vs Current Budget Comparison Report

> A custom ALV report that places the original budget, supplements, returns, budget transfers, current budget and plan cost of each WBS element side by side and flags the gap between plan and budget. Project control teams see in one list which WBS element is underfunded and how much the budget has changed since the start.

- Type: Report, Custom development, ALV report
- Module: PS
- Estimated effort: S (3–4 working days)
- Last updated: 2026-11-17
- URL: https://nekuhub.com/en/reports/wbs-plan-cost-original-current-budget-report/


## Why is the standard not enough?

CJ31 shows the budget of one project and CJ40/CJR2 its plan, on separate screens. S_ALR_87013558 gives the current budget and actuals, but it does not show original budget, supplements, returns and transfers in separate columns and does not flag the gap between plan cost and budget. Teams usually merge this table in Excel. The custom report splits the budget by transaction type and runs the multi-project comparison in one go.

### Closest standard alternatives

- CJ31: Shows the budget of one project; no list with supplement/transfer split and plan comparison.
- S_ALR_87013558: Gives current budget, actual and commitment; original budget and budget movements are not separate columns.

## Tables used

| Table | Role | Access | Join | System |
|---|---|---|---|---|
| PRPS | WBS element: external number, description, level (driving table) | Read | - | ECC + S/4 |
| PROJ | Project definition | Read | PROJ-PSPNR = PRPS-PSPHI | ECC + S/4 |
| BPGE | Overall budget values by business transaction (original, supplement, return, transfer) | Read | BPGE-OBJNR = PRPS-OBJNR | ECC + S/4 |
| BPJA | Annual budget values by business transaction | Read | BPJA-OBJNR = PRPS-OBJNR | ECC + S/4 |
| COSP | Plan cost (WRTTP 01, plan version) | Read | COSP-OBJNR = PRPS-OBJNR | ECC + S/4 |
| I_WBSElementBasicData | CDS view that can replace PRPS in S/4HANA | Read | WBSElementInternalID = PRPS-PSPNR | S/4HANA only |

## Selection screen parameters

| Parameter | Description | Type | Reference field | Required |
|---|---|---|---|---|
| S_PSPID | Project | Range / multiple | PROJ-PSPID | Yes |
| S_POSID | WBS element | Range / multiple | PRPS-POSID | No |
| S_VERNR | Responsible person number | Range / multiple | PRPS-VERNR | No |
| P_VERSN | Plan version | Single value | COSP-VERSN | Yes |
| R_OVER | Overall values | Radio button | - | No |
| R_YEAR | Annual values | Radio button | - | No |
| P_GJAHR | Fiscal year (for annual view) | Single value | BPJA-GJAHR | No |
| P_FLAG | Flagged WBS elements only | Checkbox | - | No |

## Output columns

| Column | Source |
|---|---|
| Project | PROJ-PSPID |
| WBS element | PRPS-POSID |
| Description | PRPS-POST1 |
| Level | PRPS-STUFE |
| Original budget | Calculated: BPGE/BPJA-WTGES/WTJHR, VORGA = original budget |
| Supplements | Calculated: Total of VORGA = supplement values |
| Returns | Calculated: Total of VORGA = return values |
| Net transfers | Calculated: Receiving transfers − sending transfers |
| Current budget | Calculated: Original + supplements − returns + net transfers |
| Plan cost | Calculated: Σ COSP plan (WRTTP 01, selected version) |
| Plan − budget | Calculated: Plan cost − current budget |
| Budget change % | Calculated: (Current budget − original budget) ÷ original budget × 100 |
| Currency | BPGE-TWAER |
| Flag | Calculated: Plan > budget: underfunded; budget > plan × ratio: idle budget |

## How does the report work?

1. PROJ and PRPS are read by project, WBS element and responsible person.
2. In the overall view BPGE, in the annual view BPJA for the selected fiscal year, budget values (WRTTP 41) are read and split by business transaction (VORGA): original budget, supplement, return, sending and receiving transfer.
3. Current budget = original + supplements − returns + incoming transfers − outgoing transfers.
4. Plan cost is taken from the COSP plan values (WRTTP 01) of the selected plan version, overall or per year.
5. The plan − current budget difference and the change in % versus the original budget are calculated. If plan exceeds budget, an "underfunded" flag is set; if budget exceeds plan by more than a given ratio, an "idle budget" flag is set. The ALV shows subtotals per project and WBS level.

## Authorization objects

- C_PROJ_KOK: Project display authorization by controlling area
- C_PRPS_KOK: WBS element authorization by controlling area

## Frequently asked questions

### Are budget transfers counted twice?

No. On the sending WBS element the outgoing transfer is negative and on the receiving one the incoming transfer is positive. Within the project total both sides cancel out; only transfers between projects change the project total.

### Can I see who changed the budget?

This report splits the amounts by business transaction. For user and date per document, the budget document header can be read to add a document-level list to the report; this adds 1–2 days to the estimate.

### Does it work on S/4HANA?

Yes. The classic PS budget (BPGE, BPJA) is still used in S/4HANA. Plan cost is read from the COSP compatibility view; if the new planning solution is used, plan is taken from ACDOCP.

---