# WBS Technical Completion (TECO) Readiness Check Report for Open Items

> A custom ALV report that shows, on one row per WBS element that is a candidate for technical completion (TECO), whether there are open purchase orders, open requisitions, open reservations, unbilled billing plan dates and a balance still to settle. Project teams see what has to be cleared before closing, and post-closing surprises decrease.

- Type: Report, Custom development, ALV report
- Module: PS
- Estimated effort: M (5–7 working days)
- Last updated: 2026-11-17
- URL: https://nekuhub.com/en/reports/wbs-technical-completion-teco-readiness-check-report/


## Why is the standard not enough?

When the TECO status is set in CJ20N, warnings about open items appear only at that moment and element by element; there is no advance checklist for many WBS elements. CN43N lists WBS elements with their status but does not check open orders, reservations, billing plans or balances. The custom report collects all blockers in one list and separates the elements that are "ready to close".

### Closest standard alternatives

- CJ20N: Open-item warnings appear element by element and only when TECO is set; no advance bulk checklist.
- CN43N: Lists WBS elements with their status; no check of open orders, reservations, billing plans or balances.

## Tables used

| Table | Role | Access | Join | System |
|---|---|---|---|---|
| PRPS | WBS element: description, responsible person, object number (driving table) | Read | - | ECC + S/4 |
| PROJ | Project definition | Read | PROJ-PSPNR = PRPS-PSPHI | ECC + S/4 |
| JEST | System statuses: REL, TECO, CLSD | Read | JEST-OBJNR = PRPS-OBJNR | ECC + S/4 |
| EKKN | Order items with account assignment to the WBS element | Read | EKKN-PS_PSP_PNR = PRPS-PSPNR | ECC + S/4 |
| EKPO | Order item: value, deletion and delivery completed flags | Read | EKPO-EBELN = EKKN-EBELN AND EKPO-EBELP = EKKN-EBELP | ECC + S/4 |
| EBKN | Requisitions with account assignment to the WBS element | Read | EBKN-PS_PSP_PNR = PRPS-PSPNR | ECC + S/4 |
| EBAN | Requisition item: quantity and ordered quantity | Read | EBAN-BANFN = EBKN-BANFN AND EBAN-BNFPO = EBKN-BNFPO | ECC + S/4 |
| RESB | Open reservations linked to the WBS element | Read | RESB-PSPEL = PRPS-PSPNR | ECC + S/4 |
| VBAP | Sales order item assigned to the WBS element | Read | VBAP-PS_PSP_PNR = PRPS-PSPNR | ECC + S/4 |
| FPLA | Billing plan of the order | Read | FPLA-VBELN = VBAP-VBELN | ECC + S/4 |
| FPLT | Billing plan dates: value and billing status | Read | FPLT-FPLNR = FPLA-FPLNR | ECC + S/4 |
| COSP | Actual balance still to settle | Read | COSP-OBJNR = PRPS-OBJNR | ECC + S/4 |

## Selection screen parameters

| Parameter | Description | Type | Reference field | Required |
|---|---|---|---|---|
| S_PSPID | Project | Range / multiple | PROJ-PSPID | Yes |
| S_POSID | WBS element | Range / multiple | PRPS-POSID | No |
| S_VERNR | Responsible person number | Range / multiple | PRPS-VERNR | No |
| S_PBUKR | Company code | Range / multiple | PRPS-PBUKR | Yes |
| P_BALTOL | Balance tolerance | Single value | - | No |
| P_ONLYBL | Only WBS elements with blockers | Checkbox | - | No |
| P_INCTEC | Also check elements already in TECO | Checkbox | - | No |

## Output columns

| Column | Source |
|---|---|
| Project | PROJ-PSPID |
| WBS element | PRPS-POSID |
| Description | PRPS-POST1 |
| Responsible | PRPS-VERNA |
| System status | Calculated: Text of the active statuses in JEST (e.g. REL, TECO) |
| Open PO items | Calculated: Number of items with EKPO-LOEKZ and EKPO-ELIKZ blank |
| Open PO value | Calculated: Σ EKPO-NETWR (open items) |
| Open requisition items | Calculated: Number of items with EBAN-BSMNG < EBAN-MENGE and LOEKZ blank |
| Open reservations | Calculated: Number of items with RESB-KZEAR and XLOEK blank and BDMNG > ENMNG |
| Unbilled billing plan value | Calculated: Σ FPLT-FAKWR (FKSAF ≠ C) |
| Balance to settle | Calculated: Σ COSP actual (WRTTP 04), all periods |
| Currency | COSP-TWAER |
| Readiness | Calculated: Ready if all checks are clean, otherwise Blocked |
| Blocking reasons | Calculated: List of the checks that are not zero |

## How does the report work?

1. PROJ and PRPS are read by project, WBS element, responsible person and company code. Active statuses come from JEST; elements that are released (REL) but not yet TECO or CLSD remain.
2. Open orders: number and value of the EKPO items linked via EKKN-PS_PSP_PNR that are not deleted and not delivery-completed (ELIKZ blank).
3. Open requisitions: EBAN items linked via EBKN that are not deleted and whose ordered quantity is below the requisition quantity.
4. Open reservations: items linked via RESB-PSPEL without the final issue flag (KZEAR) or deletion flag and with BDMNG > ENMNG.
5. Unbilled billing plan: value of the FPLA/FPLT dates of the sales order linked to the WBS element whose billing status is not complete (FKSAF ≠ C).
6. Balance: total actual cost and revenue in COSP (WRTTP 04); above the tolerance, settlement is considered necessary. If all checks are clean the row is "ready", otherwise the blocking reasons are listed.

## Authorization objects

- C_PROJ_KOK: Project display authorization by controlling area
- C_PRPS_KOK: WBS element authorization by controlling area
- M_BEST_WRK: Order display authorization by plant

## Frequently asked questions

### Can WBS elements shown as ready be closed from the report?

The report only reads. Ready elements can be selected and passed to the mass status change program, so TECO is given only to elements without blockers.

### Why is the balance checked against a tolerance?

Small balances of a few units can remain due to exchange differences or rounding. A balance below the tolerance does not block closing but is shown as a note on the row.

### Do the same checks apply in S/4HANA?

Yes. Status management (JEST), purchasing account assignments and reservations are the same in S/4HANA. For the balance, the COSP compatibility view or ACDOCA is read; MATDOC-based stock views can also be used for reservations in S/4HANA.

---