PS Transparent table Used the same way in S/4HANA

PRTE Scheduling Data for WBS Element

Holds the basic, forecast and actual start and finish dates and durations of WBS elements. Project planners maintain these dates in CJ20N or date planning screens, or copy them from network scheduling. POSNR matches PRPS-PSPNR; join on it when building date reports.

Main fields

FieldDescriptionKey
POSNRWBS elementYes
PSPHICurrent number of the appropriate project—
PSTRTBasic start date—
PENDEBasic finish date—
ESTRTForecasted start date—
EENDEForecasted finish date—
ISTRTActual start date—
IENDEActual finish date—

Transactions working with this table

Reports using this table

No report using this table has been added to the catalog yet.