# PRTE — Scheduling Data for WBS Element

> Holds the basic, forecast and actual start and finish dates and durations of WBS elements. Project planners maintain these dates in CJ20N or date planning screens, or copy them from network scheduling. POSNR matches PRPS-PSPNR; join on it when building date reports.

- Modules: PS
- Type: Transparent table
- S/4HANA status: Used the same way in S/4HANA

- URL: https://nekuhub.com/en/tables/prte/

## Main fields

| Field | Description | Key |
|---|---|---|
| POSNR | WBS element | Yes |
| PSPHI | Current number of the appropriate project | - |
| PSTRT | Basic start date | - |
| PENDE | Basic finish date | - |
| ESTRT | Forecasted start date | - |
| EENDE | Forecasted finish date | - |
| ISTRT | Actual start date | - |
| IENDE | Actual finish date | - |

## Transactions working with this table

CJ01, CJ02, CJ03, CJ11, CJ12, CJ13, CJ20N, CJ21, CJ22, CJ23, CJ24, CJ29, CJ2B, CJ2C, CJ2D, CN24N, CN43N