CJ23 Change Forecast Dates
Changes the forecast start and finish dates of WBS elements; the basic dates are kept while the current expectation is held separately. Project managers who want a plan-versus-forecast comparison use it. Forecast dates are also stored in PRTE.
Program: SAPLCJTR
Related tables