# CN22 — Change Network

> Changes the activities, durations, work centers and components of an existing network. Project planners rerun scheduling and costing after updating the plan. Some fields cannot be changed on confirmed activities, so the confirmation may have to be cancelled first.

- Modules: PS
- Program: SAPLCOKO
- S/4HANA status: Also used in S/4HANA

- Related tables: AFKO, AFVC, AFVV, RESB
- URL: https://nekuhub.com/en/transactions/cn22/