MD01N MRP Live
Runs material requirements planning on SAP HANA with most of the planning logic executed in the database; selection can be by plant, material or product group. It is designed for shorter run times than classic MD01 and is the recommended MRP run in SAP S/4HANA. Some special planning scenarios are not handled in HANA and fall back to classic logic, so check the result log.
Program: PPH_MRP_START