PP Standard SAP Also used in S/4HANA

MD62 Change Planned Independent Requirements

Changes the quantity, date or version of existing planned independent requirements; the consumption situation can also be displayed. It is used when the forecast is updated or when unconsumed requirements of past periods are cleaned up. Unconsumed quantities in the past may still act as requirements in MRP.

Program: SAPMM60X